RE: Canceled for Now --Approved - Bldg. E17 - 4th and 5th floor v

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Dec 5 08:56:33 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU,
        E-Zone
	 <E-Zone@MIT.EDU>, Gerry Hughes <ghughes@PLANT.MIT.EDU>,
        sdverify@MIT.EDU, rmello@MIT.EDU, wardd@MIT.EDU
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, shutowns@MIT.EDU
Date: Fri, 5 Dec 1997 08:53:40 -0500

I have just been advised that this shutdown has been canceled for today.
The work will be rescheduled in the future but will be without
notification. Since this is for cooling only, the outside air will be
more than sufficient for supply ventilation. If you have any question,
please feel free to contact Mr. Gerry Hughes at 3-6335.

Thank you for your assistance in this matter.

Andrea Nichols
> Operations Center
> 8-7872
> 
> > > Status: Normal
> > > Building: E17 - 4th and 5th floor ventilation (Air Handler 2)
> > > Date: 12/5/97 Canceled for now
> > > Day: TBD
> > > Time: TBD
> > > System: Chilled water coil shutoff.
> > > Duration: 4 hours
> > > Reason: 
> > > Repack control valve (leaking)
> > > 
> > > Effect: 
> > > Loss of supply cooling on 4th and 5th floors - outside air
> > temperature
> > > should suffice for cooling.
> > > 
> > > 
> > 
> 