The following approved shutdown for Bldg. E17 - 4th & 5th Floor
Ventilation on 12/5 is for your information.

Andrea Nichols
Operations Center
8-7872

> > Status: Normal
> > Building: E17 - 4th and 5th floor ventilation (Air Handler 2)
> > Date: 12/5/97
> > Day: Friday
> > Time: 7:30 AM - 11:30 AM
> > System: Chilled water coil shutoff.
> > Duration: 4 hours
> > Reason: 
> > Repack control valve (leaking)
> > 
> > Effect: 
> > Loss of supply cooling on 4th and 5th floors - outside air
> temperature
> > should suffice for cooling.
> > 
> > 
> 