Bldg. E19 - 2nd & 3rd flrs. Perimeter Heating Shutdown Request f
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 25 11:36:22 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: MIS-Team <MIS-Team@PLANT.MIT.EDU>, Plant-All <Plant-ALL@MIT.EDU>,
schedule@MIT.EDU, cipriano@MIT.EDU, joanf@MIT.EDU, cbunker@MIT.EDU,
khiggins@MIT.EDU, steves@MIT.EDU, shutdowns@MIT.EDU, opsnote@MIT.EDU,
cust-coach@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Tue, 25 Nov 1997 11:34:51 -0500
> To: MIS-Team; Plant-All; schedule@mit.edu; cipriano@mit.edu;
> joanf@mit.edu; cbunker@mit.edu; khiggins@mit.edu; steves@ mit.edu;
> shutdowns@mit.edu; opsnote@mit.edu; cust-coach@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E19 - 2nd & 3rd flrs. Perimeter Heating Shutdown
> Request for 11/28
>
>
The following shutdown request for Bldg. E19 - 2nd & 3rd Floors
(Perimeter Heating) on 11/28 is for your information and comment. Would
you please let me know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E19 - 2nd & 3rd Floors
> Date: 11/28/97
> Day: Friday
> Time: 6:30 AM - 5:30 PM
> System: Chilled Water (A/C), heating hot water, supply-cooling (air:
> Duration: 10 hours
> Reason:
> To tie in temporary heat lines for the installation of new chilled
> water system (air conditioning)
>
> Effect:
> Loss of chilled water (A/C) and heating hot water (perimeter heat).
> There will be supply ventilation (air coming in from the outside) on
> the 2nd and 3rd floors.
>
>