Bldg. 26 - All Rooms All Steam Shutdown Request on 11/25

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Nov 20 11:39:17 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: schedule@MIT.EDU, shutdowns@MIT.EDU, adams@mitlns.mit.edu,
        gfp170@mitrlevm.mit.edu, mparker@MIT.EDU, rmbesset@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 20 Nov 1997 11:38:36 -0500

> To: 	schedule@mit.edu; shutdowns@mit.edu; adams@mitlns.mit.edu;
> gfp170@mitrlevm.mit.edu; mparker@mit.edu; rmbesset@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 26 - All Rooms All Steam Shutdown Request on 11/25
> 
> 
The following shutdown request for Bldg. 26 - all rooms) on 11/25 is for
your information and comment. Would you please let me know if this has
your approval or disapproval.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 26
> Date: 11/25/97
> Day: Tuesday
> Time: 8:00 AM - 2:00 PM
> System: All steam - (hot domestic water, heat)
> Duration: 6 hours
> Reason: 
> To install new valve onto drip line from 200 lb. trap.
> 
> Effect: 
> Losss of hot domestic (bathroom & kitchen faucets) and heating hot
> water (no heat for entire building during shutdown period.)
> 
> 