Date: Thu, 20 Nov 1997 11:38:36 -0500
> To: schedule@mit.edu; shutdowns@mit.edu; adams@mitlns.mit.edu;
> gfp170@mitrlevm.mit.edu; mparker@mit.edu; rmbesset@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 26 - All Rooms All Steam Shutdown Request on 11/25
>
>
The following shutdown request for Bldg. 26 - all rooms) on 11/25 is for
your information and comment. Would you please let me know if this has
your approval or disapproval.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 26
> Date: 11/25/97
> Day: Tuesday
> Time: 8:00 AM - 2:00 PM
> System: All steam - (hot domestic water, heat)
> Duration: 6 hours
> Reason:
> To install new valve onto drip line from 200 lb. trap.
>
> Effect:
> Losss of hot domestic (bathroom & kitchen faucets) and heating hot
> water (no heat for entire building during shutdown period.)
>
>