[40734] in Hotline Meeting
FW: Approved -W61 Shutdown Request for 11/21
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Nov 17 10:26:29 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: mwhelan@MIT.EDU, kcn@MIT.EDU, neil.tomlinson@MIT.EDU, dcarlson@MIT.EDU,
cappucci@MIT.EDU, cust-coach@MIT.EDU, mmahoney@MIT.EDU,
sdverify@MIT.EDU, shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu, D-Zone <D-Zone@MIT.EDU>
Date: Mon, 17 Nov 1997 10:25:17 -0500
The following approved W61 Bldg. shutdown on 11/21 is for your
information.
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: W61
> > Date: 11/21/97
> > Day: Friday
> > Time: 1:00 PM - 2:00 PM
> > System: All electric lighting and power except emergency power
> > Duration: 1 hour
> > Reason:
> > To install metering equipment on electrical switchgear
> >
> > Effect:
> > Loss of power: access controls, bldg. power, elevators, computers,
> > telephones and lighting; air: supply ventilation, cooling, heating,
> > exhaust - general, exhaust - toilet, compressed control air; steam:
> > condensate return.
> >
> >
>