[40709] in Hotline Meeting
Bldg. E51 Shutdown Request for 11/25
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 14 11:54:06 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: shutdowns@MIT.EDU, mmarshal@MIT.EDU, lhill@MIT.EDU, dimauro@MIT.EDU,
dlrooks@MIT.EDU, jstein@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 14 Nov 1997 11:53:41 -0500
> To: shutdowns@mit.edu; mmarshal@mit.edu; lhill@mit.edu;
> dimauro@mit.edu; dlrooks@mit.edu; jstein@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. E51 Shutdown Request for 11/25
>
>
The following shutdown request for Bldg. E51 on 11/25 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E51
> Date: 11/25/97
> Day: Tuesday
> Time: 6:00 AM - 7:00 AM
> System: Electric lighting and power: 208/120V substation only - 480V
> power will be on.
> Duration: 1 hour
> Reason:
> To install metering equipment on the electrical switchgear
>
> Effect:
> Loss of Power: access controls, building power, elevators, computers,
> telephones, lighting; Water: chilled water, Air: supply ventilation,
> cooling, heating, exhaust - general, exhaust - toilet, compressed
> control air; steam: condensate return
>
>