Bldg. 36 - 433 and North Offices - 2 - 8th floors on 11/12

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 7 16:27:39 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: schedule@MIT.EDU, rroscoe@MIT.EDU, gfp170@mitrlevm.mit.edu,
        shutdowns@MIT.EDU, opsnote@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 7 Nov 1997 16:27:13 -0500

> To: 	schedule@mit.edu; rroscoe@mit.edu; gfp170@mitrlevm.mit.edu;
> shutdowns@mit.edu; opsnote@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 36 - 433 and North Offices - 2 - 8th floors on
> 11/12
> 
> 
The following shutdown request for Bldg. 36 - 433 and north offices on
floors 2 - 8 on 11/12 is for your information and comment. Would you
please let me know if this has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872 

> Status: Normal
> Building: 36  - 433 and north offices on floors 2 thru 8
> Date: 11/12/97
> Day: Wednesday
> Time: 9:00 AM - 12 noon
> System: Air Handler 7 - PM#702034 - supply ventilation, cooling and
> heating
> Duration: 3 hours
> Reason: 
> Repair dampers
> 
> Effect: 
> Loss of supply ventilation, supply cooling and supply heating during
> 3-hour shutdown.
> 
> 