[40589] in Hotline Meeting
Bldg. 36 - 433 and North Offices - 2 - 8th floors on 11/12
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 7 16:27:39 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: schedule@MIT.EDU, rroscoe@MIT.EDU, gfp170@mitrlevm.mit.edu,
shutdowns@MIT.EDU, opsnote@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 7 Nov 1997 16:27:13 -0500
> To: schedule@mit.edu; rroscoe@mit.edu; gfp170@mitrlevm.mit.edu;
> shutdowns@mit.edu; opsnote@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 36 - 433 and North Offices - 2 - 8th floors on
> 11/12
>
>
The following shutdown request for Bldg. 36 - 433 and north offices on
floors 2 - 8 on 11/12 is for your information and comment. Would you
please let me know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 36 - 433 and north offices on floors 2 thru 8
> Date: 11/12/97
> Day: Wednesday
> Time: 9:00 AM - 12 noon
> System: Air Handler 7 - PM#702034 - supply ventilation, cooling and
> heating
> Duration: 3 hours
> Reason:
> Repair dampers
>
> Effect:
> Loss of supply ventilation, supply cooling and supply heating during
> 3-hour shutdown.
>
>