[40586] in Hotline Meeting
Bldg. 1 Electric Lighting and Power Shutdown Request for 11/14
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Nov 7 11:57:54 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: schedule@MIT.EDU, shutdowns@MIT.EDU, mgibson@MIT.EDU, patdixon@MIT.EDU,
jdb@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Fri, 7 Nov 1997 11:57:27 -0500
> To: schedule@mit.edu; shutdowns@mit.edu; mgibson@mit.edu;
> patdixon@mit.edu; jdb@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 1 Electric Lighting and Power Shutdown Request for
> 11/14
>
>
The following shutdown request for Bldg. 1 on 11/14 is for your
information and comment. Would you please let me know if this has your
approvl or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 1- portions of 1st, 2nd & 3rd floors
> Date: 11/14/97
> Day: Friday
> Time: 5:00 AM - 7:00 AM
> System: Electric lighting and power (EMERGENCY will be on)
> Duration: 2 hours
> Reason:
> To install metering equipment in main switchgear in transformer room.
>
> Effect:
> Loss of access controls, bldg. power, computers, lighting, chilled
> water, supply ventilation, supply cooling, supply heating, exhaust
> laboratory, exhaust general, and exhaust toilet air.
>
>