From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: westlund@MIT.EDU, randy@MIT.EDU
Cc: shutdown@plant.mit.edu, shutdowns@MIT.EDU, cust-coach@MIT.EDU,
mmahoney@MIT.EDU
Date: Thu, 6 Nov 1997 11:15:30 -0500
> To: westlund@mit.edu; randy@mit.edu
> Cc: shutdown@plant.mit.edu; shutdowns@mit.edu; cust-coach@mit.edu;
> mmahoney@mit.edu
> Subject: Bldg. 9 Lower Basement- 0052, 0053 & 0054, 0055 and
> 0030, Lobby, 0050 and 9-150
>
>
The following shutdown request for Bldg. 9 (see above for room listings)
on 11/17 up to and including 12/4 is for your information and comment.
Would you please let me know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 9 - lower basement - 0052, 0053, 0054, 0055, 0030, lobby,
> 0050 and 9-150
> Date: 11/17/97
> Day: Monday
> Time: 7:00 AM - 11:00 PM every day during shutdown period
> System: supply ventilation, supply cooling and supply heating (Air
> Handler 2 & all assoc. fans & ducts
> Duration: 16 hours each day
> Reason:
> Asbestos removal of tiles in above listed rooms. Removal of Air
> Handler 2 and all associated fans and ducts which serve the basement
> and 9-150 in supplying ventilation, cooling and heating.
>
> Effect:
> Loss of supply ventilation, cooling and heating. There will be no
> access to rooms 0052, 0053 and 0054. There will be access to the motor
> control center (0050) which will be available via a tunnel. Otherwise
> ... 0050 will be inaccessible. Accesss to rooms 0055 and 0030 will be
> via stair #000SB only.
>
>