[40521] in Hotline Meeting
Bldgs. E17 and E18 Shutdown Request for 11/8 - Bathroom, Kitchen
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 4 15:24:22 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Plant-All <Plant-ALL@MIT.EDU>, wardd@MIT.EDU, aufiero@MIT.EDU,
rmelo@MIT.EDU, shyoung@MIT.EDU, jmganno@MIT.EDU, jean@crc.mit.edu,
rmoore@MIT.EDU, mparker@MIT.EDU, bethannt@MIT.EDU, jmedeiro@MIT.EDU,
shutdowns@MIT.EDU, cust-coach@MIT.EDU, opsnote@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Tue, 4 Nov 1997 15:20:33 -0500
> To: Plant-All; wardd@mit.edu; aufiero@mit.edu; rmelo@mit.edu;
> shyoung@mit.edu; jmganno@mit.edu; jean@crc.mit.edu; rmoore@mit.edu;
> mparker@mit.edu; bethannt@mit.edu; jmedeiro@mit.edu;
> shutdowns@mit.edu; cust-coach@mit.edu; opsnote@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldgs. E17 and E18 Shutdown Request for 11/8 - Bathroom,
> Kitchen Facilities and Drinking Fountains
>
>
The second shutdown request for Bldgs. E17 and E18 on 11/8 is for your
information and comment. Would you let me know if this has your approval
or not.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E17 and E18
> Date: 11/8/97
> Day: Saturday
> Time: 6:00 AM 2:00 PM or longer
> System: Hot and cold domestic water
> Duration: 8 or more hours
> Reason:
> To check for cross connections between domestic and lab process water.
>
> Effect:
> Loss of hot and cold domestic water only (drinking water; kitchen and
> bathroom facilities).
>
>