RE: Approved E17 and E18 1 - 6 floors shutdown request for 11/5

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 4 13:31:41 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU,
        Dan Crovo
	 <DCrovo@PLANT.MIT.EDU>, Robert Carr <rcarr@PLANT.MIT.EDU>,
        Richard Finn
	 <RFinn@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, Plant-All <Plant-ALL@MIT.EDU>,
        jmganno@MIT.EDU, shyoung@MIT.EDU, aufiero@MIT.EDU, rmelo@MIT.EDU,
        mparker@MIT.EDU, bethannt@MIT.EDU, dshea@MIT.EDU, wardd@MIT.EDU,
        opsnote@MIT.EDU, shutdowns@MIT.EDU, Cust-Coach <cust-coach@MIT.EDU>
Date: Tue, 4 Nov 1997 13:27:36 -0500

The approved rescheduled shutdown for Bldg. E17 & E18 - 1-6 floors is
now on 11/5.

Thank you.

Andrea Nichols
Operations Center
8-7872

> ----------
> > Status: Normal
> > Building: E17 & E18 Floors 1 thru 6 
> > Date: 11/5/97
> > Day: Wednesday
> > Time: 6:00 AM - 7:30 AM
> > System: Hot domestic water, heating hot water, supply heating,
> medium
> > and low pressure steam and condensate return
> > Duration: 1 hour (15 - 20 minutes within above time frame.
> > Reason: 
> > Remove autoclave from E17 - 511A and reinstall it in E17 - 537. Must
> > cut/cap/plug equipment.
> > 
> > Effect: 
> > Loss of hot domestic and heating hot water; loss of supply heating
> and
> > loss of medium and low pressure steam as well as condensate return.
> > 
> > 
> 