[40515] in Hotline Meeting
RE: Approved E17 and E18 1 - 6 floors shutdown request for 11/5
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Nov 4 13:31:41 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU,
Dan Crovo
<DCrovo@PLANT.MIT.EDU>, Robert Carr <rcarr@PLANT.MIT.EDU>,
Richard Finn
<RFinn@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, Plant-All <Plant-ALL@MIT.EDU>,
jmganno@MIT.EDU, shyoung@MIT.EDU, aufiero@MIT.EDU, rmelo@MIT.EDU,
mparker@MIT.EDU, bethannt@MIT.EDU, dshea@MIT.EDU, wardd@MIT.EDU,
opsnote@MIT.EDU, shutdowns@MIT.EDU, Cust-Coach <cust-coach@MIT.EDU>
Date: Tue, 4 Nov 1997 13:27:36 -0500
The approved rescheduled shutdown for Bldg. E17 & E18 - 1-6 floors is
now on 11/5.
Thank you.
Andrea Nichols
Operations Center
8-7872
> ----------
> > Status: Normal
> > Building: E17 & E18 Floors 1 thru 6
> > Date: 11/5/97
> > Day: Wednesday
> > Time: 6:00 AM - 7:30 AM
> > System: Hot domestic water, heating hot water, supply heating,
> medium
> > and low pressure steam and condensate return
> > Duration: 1 hour (15 - 20 minutes within above time frame.
> > Reason:
> > Remove autoclave from E17 - 511A and reinstall it in E17 - 537. Must
> > cut/cap/plug equipment.
> >
> > Effect:
> > Loss of hot domestic and heating hot water; loss of supply heating
> and
> > loss of medium and low pressure steam as well as condensate return.
> >
> >
>