[40441] in Hotline Meeting
RE: Rescheduled Request Bldgs. 34 and 36 shutdown request now for
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Oct 30 14:41:41 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'rroscoe@mit.edu'"
<rroscoe@MIT.EDU>,
"'mbrooks@mit.edu'" <mbrooks@MIT.EDU>,
"'gfp170@mitrlevm.mit.edu'" <gfp170@mitrlevm.mit.edu>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
Andrea Nichols
<andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
Neil Tomlinson
<NTomlins@PLANT.MIT.EDU>
Date: Thu, 30 Oct 1997 14:38:43 -0500
> It has been requested that this shutdown for Bldgs. 34 and 36 now take
> place on 11/7. Would you please let me know if this would fit your
> schedules.
>
> Thank you again.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 34 and 36
> > Date: 11/7/97
> > Day: Friday
> > Time: 3:00 AM - 9:00 AM
> > System: All steam heating hot water, hot domestic water also
> > Duration: 6 hours
> > Reason:
> > Repair steam valve (Bonnett Gasket)
> >
> > Effect:
> > Loss of all steam (heating hot water and domestic hot water
> (restroom
> > & kitchen faucets)
>
>
>