[40142] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE:Revised Rescheduled Bldg. 56 - Emergency Electric Standby - Sa

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Oct 20 14:40:58 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'mparker@mit.edu'" <mparker@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
        "'juliec@mit.edu'" <juliec@MIT.EDU>,
        "'lindlore@mit.edu'"
	 <lindlore@MIT.EDU>,
        "'jmganno@mit.edu'" <jmganno@MIT.EDU>,
        "'loudib@mit.edu'" <loudib@MIT.EDU>,
        "'claudia@mit.edu'"
	 <claudia@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'pguyer@mit.edu'"
	 <pguyer@MIT.EDU>, "'rha@mit.edu'" <rha@MIT.EDU>,
        "'bmalone@mit.edu'"
	 <bmalone@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
        Neil Tomlinson
	 <NTomlins@PLANT.MIT.EDU>
Date: Mon, 20 Oct 1997 14:38:08 -0400

There have been a few requests for other dates and times for this
particular shutdown that have not been acceptable to other departments
in Bldg. 56. The contractor is available on Saturday, November 1 from
7:00 AM - 7:00 PM. Would you please let me know if this will be all
right with your schedules.

Thank you again for your time.
> 	Andrea Nichols
> 	Operations Center
> 	8-7872
> 
> 	> Status: Normal
> 	> Building: 56
> 	> Date: 11/01
> 	> Day: Saturday
> 	> Time: 7:00 AM - 7:00 PM
> 	> System: Electrical (Lifesafety circuits)
> 	> Duration: 12 hours
> 	> Reason: 
> 	> Move control panel down 2 feet to eye level
> 	> 
> 	> Effect: 
> 	> There will be no power (emergency or normal) shut down during
> this
> 	> period. However the emergency generator will be out of service
> for the
> 	> 12 hour period. This means that in the event of a power outage
> there
> 	> will be NO exit lights, corridor lights, emergency (red)
> outlets in
> 	> labs, control air compressor, sum pumps, etc.
> 	> 
> 	 
> 
> 