[40036] in Hotline Meeting
Bldg. 56 - Emergency Electric Standby - 10/21 PM - 22 AM
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 15 12:03:26 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: mparker@MIT.EDU, mbj@MIT.EDU, juliec@MIT.EDU, lindlore@MIT.EDU,
jmganno@MIT.EDU, loudib@MIT.EDU, claudia@MIT.EDU, schedule@MIT.EDU,
shutdowns@MIT.EDU, pguyer@MIT.EDU, micheled@MIT.EDU, rha@MIT.EDU,
bmalone@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Wed, 15 Oct 1997 12:00:59 -0400
> To: mparker@mit.edu; mbj@mit.edu; juliec@mit.edu; lindlore@mit.edu;
> jmganno@mit.edu; loudib@mit.edu; claudia@mit.edu; schedule@mit.edu;
> shutdowns@mit.edu; pguyer@mit.edu; micheled@mit.edu; rha@mit.edu;
> bmalone@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 56 - Emergency Electric Standby - 10/21 PM - 22 AM
>
>
The following shutdown for Bldg. 56 is for your information and comment.
Would you please let me know if this has your approval or not.
Please note: We ask that ALL occupants of the building leave during the
shutdown period of 6:00 PM 10/21 thru 6:00 AM on 10/22. If this is not
possible, we can change the 12 hour period from 7:00 PM - 7:00 AM or on
a weekend. But this must be done and no one can be in the building. If
someone is in the building, we must know who and where this person/s
will be working.This is mandated by law.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 56
> Date: 10/21/22
> Day: Tuesday
> Time: 6:00 PM - 6:00 AM
> System: Electrical (Lifesafety circuits)
> Duration: 12 hours
> Reason:
> Move control panel down 2 feet to eye level
>
> Effect:
> There will be no power (emergency or normal) shut down during this
> period. However the emergency generator will be out of service for the
> 12 hour period. This means that in the event of a power outage there
> will be NO exit lights, corridor lights, emergency (red) outlets in
> labs, control air compressor, sum pumps, etc.
>
>
>
>