[40034] in Hotline Meeting
Bldg. 14 Penthouse South Area Asbestos Removal Notification for
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Oct 15 10:12:19 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: ELWORTHI@MIT.EDU, efc@MIT.EDU, ninadm@MIT.EDU, rks@MIT.EDU,
sdl-adm-lib@mit.edu", tat@mit.edu, A-Zone <A-Zone@MIT.Edu>,
sdverify@mit.edu, Jack Narcotta <JNarcott@PLANT.MIT.EDU>,
shutdowns@mit.edu, mmahoney@mit.edu, tr6@mit.edu"
Cc: shutdown@plant.mit.edu
Date: Wed, 15 Oct 1997 10:09:50 -0400
> To: ELWORTHI@MIT.EDU; efc@mit.edu; ninadm@mit.edu; rks@mit.edu;
> sdl-adm-lib@mit.edu"; tat@mit.edu; A-Zone; sdverify@mit.edu; Jack
> Narcotta; shutdowns@mit.edu; mmahoney@mit.edu; tr6@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 14 Penthouse South Area Asbestos Removal
> Notification for 10/27 thru 10/31
>
>
The following asbestos notification for Bldg. 14 Penthouse on 10/27 thru
10/31 is for your information. If you have a concern, please feel free
to contact Mr. Jack Narcotta at 3-6352.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 14 Penthouse South Area- Air Handler /Cooler 4
> Date: 10/27/31
> Day: Monday
> Time: 7:00 AM - 5:00 PM each day
> System: None - no affect on system operations
> Duration: 5 days
> Reason:
> To remove asbestos pipe covering and duct covering on Air Handler/Air
> Cooler 4
>
> Effect:
> None - to effect on air supply system - asbestos removal notification
> only
>
>