FW:Approved - 18 - 480V Power Shutdown Request for 9/17
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 12 10:07:15 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU,
A-Zone
<A-Zone@MIT.EDU>, Manuel Moreira <mmoreira@PLANT.MIT.EDU>,
sdverify@MIT.EDU
Cc: shutdown@plant.mit.edu, shutowns@MIT.EDU, custcoach@MIT.EDU,
opsnote@MIT.EDU, mbj@MIT.EDU
Date: Fri, 12 Sep 1997 10:03:53 -0400
The following approved shutdown for Bldg. 18 - 480V Power on 9/17 is for
your information .
Andrea Nichols
Operations Center
8-7872
> > Status: Normal
> > Building: 18
> > Date: 9/17/97
> > Day: Wednesday
> > Time: 4:00 AM - 7:00 AM
> > System: 480V Power - all lab & head lights
> > Duration: 3 hours
> > Reason:
> > To install new breaker to distribution panel in subbasement of Bldg.
> > 18.
> >
> > Effect:
> > Loss of elevators, lighting, chilled water, hot and cold domestic
> > water, also de-ionized water. Also affected will be supply
> > ventilation, cooling, heating, exhaust general air, toilet exhaust
> > air, compressed lab air and lab vacuum air.
> >
> >
>