[39453] in Hotline Meeting
FW: 50, 51, 14, 14S, 2, 4, 6 & 8 Shutdown Request for 9/12 - midn
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Sep 5 12:46:32 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: shutdowns@MIT.EDU
Date: Fri, 5 Sep 1997 12:45:24 -0400
Carleton--
Here it is ...
Thanks.
Andrea
> The following shutdown request for Buildings 50, 51, 14, 14S 2, 4, 6 &
> 8 for
> 9/12 from midnight to 12:15 AM is for your information and comment.
> Would you please let me know if this has your approval or not.
>
> Thank you.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 50, 51, 14, 14S 2, 4, 6, 8
> > Date: 9/12/97
> > Day: Friday
> > Time: Midnight to 12:15 AM
> > System: Normal Electrical Power
> > Duration: 15 minutes
> > Reason:
> > Switching of 6B G & W
> >
> > Effect:
> > Loss of Power: builidng, elevators, computers & lighting; Air:
> supply
> > ventilation, cooling, heating, laboratory exhaust air, toilet
> exhaust
> > air, compressed control air, compressed lab air, lab vacuum air and
> > Steam: condensate return
> >
> >
>