[39432] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldgs. 1, 3 and 5 Extended Emergency Shutdown - Now up to and inc

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Sep 4 12:41:50 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU, schedule@MIT.EDU,
        pmccosco@MIT.EDU, mgibson@MIT.EDU, magowen@MIT.EDU, mamullow@MIT.EDU,
        patdixon@MIT.EDU, fenner@MIT.EDU, jobrien@MIT.EDU, chm@MIT.EDU,
        dory@MIT.EDU, annab@MIT.EDU, cust-coach@MIT.EDU, decarli@MIT.EDU,
        sburke@MIT.EDU, skendall@MIT.EDU, mleen@MIT.EDU,
        C-Zone <C-Zone@MIT.EDU>, Jack Narcotta <JNarcott@PLANT.MIT.EDU>,
        shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 4 Sep 1997 12:40:38 -0400

> To: 	dcarlson@mit.edu; cappucci@mit.edu; mmahoney@mit.edu;
> schedule@mit.edu; pmccosco@mit.edu; mgibson@mit.edu; magowen@mit.edu;
> mamullow@mit.edu; patdixon@mit.edu; fenner@mit.edu; jobrien@mit.edu;
> chm@mit.edu; dory@mit.edu; annab@mit.edu; cust-coach@mit.edu;
> decarli@mit.edu; sburke@mit.edu; skendall@mit.edu; mleen@mit.edu;
> C-Zone; Jack Narcotta; shutdowns@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldgs. 1, 3 and 5 Extended Emergency Shutdown - Now up
> to and including 9/5
> 
> 
The following emergency shutdown for Bldgs. 1, 3 and 5  has now been
extended to  9/5 (formerly 9/4)  at 3:00 PM and is for your information.

Thank you.

Andrea Nichols
Operations Center
8-7872

> Status: Emergency
> Building: 1, 3 and 5
> Date: 9/5/97
> Day: Tuesday
> Time: 12 Noon - 3:00 PM 
> System: High pressure steam - domestic hot water
> Duration: 3 days
> Reason: 
> To repair high pressure steam leaks
> 
> Effect: 
> Loss of high pressure steam which means that there will not be any hot
> domestic water affecting bathroom and kitchen faucets 
> 
> 