Power Outage

daemon@ATHENA.MIT.EDU (MICHAEL ST.CROIX)
Fri Aug 8 17:27:02 1997

Date: Fri, 8 Aug 1997 03:48 EDT
From: "MICHAEL ST.CROIX" <MSTCROIX%MITPPL.bitnet@mitvma.mit.edu>
To: plant-notify@MIT.EDU
X-Envelope-To: plant-notify@mit.edu
X-Vms-To: IN%"plant-notify@mit.edu"

At approximately 5:40pm, the MIT campus experienced a major electrical
outage resulting from a fault out of the Comm. Elec. Kendall
Sub-Station.  Power was restored at 7:00pm for a short period before a
second outage was experienced.  This resulted from a failure in a
second Comm. Elec. Sub-Station at Putnam. By 10:00pm the power was
completely restored to the campus.
                                          Stephen P. Miscowski
                                          Manager of R & M