[39087] in Hotline Meeting
Emergency Shutdown - Bldgs. 3, 4 and 10 - 8/8
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Aug 8 08:23:35 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: shutdowns@MIT.EDU, pmccosco@MIT.EDU, rmallen@MIT.EDU, dory@MIT.EDU,
annab@MIT.EDU, mamullow@MIT.EDU, cust-coach@MIT.EDU, ndk@MIT.EDU,
decarli@MIT.EDU, fenner@MIT.EDU, juliec@MIT.EDU, acherron@MIT.EDU,
cwilkes@MIT.EDU, rroscoe@MIT.EDU, cehart@MIT.EDU, sheahan@MIT.EDU,
naylor@MIT.EDU, rrhonda@MIT.EDU, lpaul@MIT.EDU, heatherm@MIT.EDU,
mleen@MIT.EDU, genh@MIT.EDU, jobrien@MIT.EDU, otten@MIT.EDU,
dhenry5@MIT.EDU, scrowley@MIT.EDU
Cc: shutdown@plant.mit.edu, dcarlson@MIT.EDU, cappucci@MIT.EDU,
mmahoney@MIT.EDU, c-zone@MIT.EDU, sdverify@MIT.EDU
Date: Fri, 8 Aug 1997 08:19:39 -0400
> To: shutdowns@mit.edu; pmccosco@mit.edu; rmallen@mit.edu;
> dory@mit.edu; annab@mit.edu; mamullow@mit.edu; cust-coach@mit.edu;
> ndk@mit.edu; decarli@mit.edu; fenner@mit.edu; juliec@mit.edu;
> acherron@mit.edu; cwilkes@mit.edu; rroscoe@mit.edu; cehart@mit.edu;
> sheahan@mit.edu; naylor@mit.edu; rrhonda@mit.edu; lpaul@mit.edu;
> heatherm@mit.edu; mleen@mit.edu; genh@mit.edu; jobrien@mit.edu;
> otten@mit.edu; dhenry5@mit.edu; scrowley@mit.edu
> Cc: shutdown@plant.mit.edu; dcarlson@mit.edu; cappucci@mit.edu;
> mmahoney@mit.edu; c-zone@mit.edu; sdverify@mit.edu
> Subject: Emergency Shutdown - Bldgs. 3, 4 and 10 - 8/8
>
>
The following emergency shutdown for Bldgs. 3, 4 and 10 for today (8/8)
is for your information.
Andrea Nichols
Operations Center
8-7872
> Status: Emergency
> Building: 3, 4 and 10
> Date: 8/8/97
> Day: Friday
> Time: 8:10 AM - ASAP
> System: Domestic hot water
> Duration: TBD
> Reason:
> Leaking valve
>
> Effect:
> Loss of domestic hot water (bathroom and kitchen faucets).
>
>