RE: Shutdown Building 11 8 hrs & Bldgs. 1, 3, 5, 7, 10 for 2 hour
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Aug 5 09:47:22 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: To:schedule@MIT.EDU, shutdowns@MIT.EDU, pmccosco@MIT.EDU, mgibson@MIT.EDU,
magowen@MIT.EDU, mamullow@MIT.EDU, patdixon@MIT.EDU, jobrien@MIT.EDU,
annab@MIT.EDU, admitmb@mitvmc.mit.edu, dory@MIT.EDU,
cust-coach@MIT.EDU, decarli@MIT.EDU, fenner@MIT.EDU, sburke@MIT.EDU,
skendall@MIT.EDU, herbert@MIT.EDU, mleen@MIT.EDU, cwm@MIT.EDU,
kbarrett@MIT.EDU, rdavies@MIT.EDU, cwilkes@MIT.EDU, rchambe@MIT.EDU,
src@MIT.EDU, rhwill@MIT.EDU, rhondar@MIT.EDU, rroscoe@MIT.EDU,
otten@MIT.EDU, dhenry5@MIT.EDU, graham@MIT.EDU, hogue@MIT.EDU,
jean@MIT.EDU, cod@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Tue, 5 Aug 1997 09:43:35 -0400
I wanted to let you know that it has been requested that this
shutdown take place on a weekend, preferably a Saturday. As soon as I
have more information I will pass it on to you.
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 1, 3, 5, 7, 10 & 11
> > Date: 8/??/97
> > Day: Saturday
> > Time: 5:00 AM - 1:00 PM *
> > System: Emergency power & lighting
> > Duration: 8 hrs. for Bldg. 11 - 8 hrs. for 1, 3, 5, 7 & 10 for 2
> hrs.
> > Reason:
> > Switch system over to new emergency system
> >
> > Effect:
> > Loss of Power: emergency, elevators, telephones, corridors/stairs
> > lighting, athena equip; steam: condensate return (Bldg. 3); Fire
> > alarm. This will affect Bldg. 11 from 5:00 AM - 1:00 PM. It will
> > affect Bldgs. 1, 3, 5, 7 and 10 from 7:00 AM - 9:00 AM
>
>
>