[38864] in Hotline Meeting
RE:Rescheduled Bldg. 26 - Request for Normal Electrical Power Shu
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jul 14 16:04:40 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'gfp170@mitrlevm.mit.edu'" <gfp170@mitrlevm.mit.edu>,
"'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'rmbessette@mit.edu'" <rmbessette@MIT.EDU>,
"'dudley@mit.edu'" <dudley@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>,
William Wohlfarth
<wpwohlfa@PLANT.MIT.EDU>, Plant@MIT.EDU
Date: Mon, 14 Jul 1997 16:01:30 -0400
It has been brought to my attention that the special equipment ordered
for this shutdown will not arrive in time for the approved shutdown. A
new date has been requested (7/24 PM - 7/25 AM). Would you please let me
know if this has your approval or not.
Thank you for your patience and I look forward to hearing from you.
> Andrea Nichols
> Operations Center
> 8-7872
>
> Status: Normal
> Building: 26
> Date: 7/24 - 7/25 (formerly 7/17 PM - 7/18 AM)
> Day: Thursday
> Time: 11:00 PM - 7:00 AM
> System: Normal Electrical Power
> Duration: 8 hours
> Reason:
> Final phase of New 15KV switch installation. .
>
> Effect:
> >Loss of Power: access controls, building power, elevators,
> computers,
> >telephones and lighting; Water: hot domstic water only; Air:
> supply
> >ventilation, supply cooling, supply heating, laboratory exhaust
> air, general
> exhaust air and toilet exhaust air.
>
>
>
>