[38839] in Hotline Meeting

home help back first fref pref prev next nref lref last post

RE: Correction--Bldg. 1 - 225, 229, 229A, 235, 237E, 245 & 249 Sh

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 10 14:50:42 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: mamullow@MIT.EDU, patdixon@MIT.EDU, mgibson@MIT.EDU, shutdowns@MIT.EDU,
        Cust-Coach <cust-coach@MIT.EDU>, Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Thu, 10 Jul 1997 14:47:44 -0400

Correction to shutdown request for Bldg. 1 - 225, 229, 229A, 235, 237E,
245 and 249. Building power will not be off -- only computers, lighting
and fan coil units in the above-mentioned rooms.

Sorry for the confusion.

Thank you.
Andrea Nichols
Operations Center
8-7872
> ----------
> From: 	Andrea Nichols
> Sent: 	Thursday, July 10, 1997 9:56 AM
> To: 	mamullow@mit.edu; patdixon@mit.edu; mgibson@mit.edu;
> shutdowns@mit.edu; Cust-Coach
> Cc: 	Shutdown
> Subject: 	Bldg. 1 - 225, 229, 229A, 235, 237E, 245 & 249 Shutdown
> Request for 7/17
> Importance: 	High
> 
> The following shutdown request for Bldg. 1 - see above-mentioned rooms
> on 7/17 is for your information and comment. Would you please let me
> know if this has your approval or disapproval.
> 
> Thanks very much.
> 
> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 1-225, 229, 229A, 235, 237E, 245 & 249
> > Date: 7/17/97
> > Day: Thursday
> > Time: 4:00 AM - 8:00 AM
> > System: Electrical Power
> > Duration: 4 hours
> > Reason: 
> > To make repairs to the panel that feeds this area.
> > 
> > Effect: 
> > Loss of power: computers, lighting and fan coil units;
> > Air: supply ventilation
> > 
> > 
> 

home help back first fref pref prev next nref lref last post