[38833] in Hotline Meeting
Bldg. 1 - 225, 229, 229A, 235, 237E, 245 & 249 Shutdown Request f
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 10 09:59:45 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: mamullow@MIT.EDU, patdixon@MIT.EDU, mgibson@MIT.EDU, shutdowns@MIT.EDU,
cust-coach@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 10 Jul 1997 09:56:47 -0400
> To: mamullow@mit.edu; patdixon@mit.edu; mgibson@mit.edu;
> shutdowns@mit.edu; cust-coach@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 1 - 225, 229, 229A, 235, 237E, 245 & 249 Shutdown
> Request for 7/17
>
>
The following shutdown request for Bldg. 1 - see above-mentioned rooms
on 7/17 is for your information and comment. Would you please let me
know if this has your approval or disapproval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 1-225, 229, 229A, 235, 237E, 245 & 249
> Date: 7/17/97
> Day: Thursday
> Time: 4:00 AM - 8:00 AM
> System: Electrical Power
> Duration: 4 hours
> Reason:
> To make repairs to the panel that feeds this area.
>
> Effect:
> Loss of power: building power, computers, lighting and fan coil units;
> Air: supply ventilation
>
>