Bldg. 11 Shutdown Request - 7/15

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 8 14:14:02 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: graham@MIT.EDU, jean@MIT.EDU, hogue@MIT.EDU, rhwill@MIT.EDU,
        shutdowns@MIT.EDU, schedule@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Tue, 8 Jul 1997 14:11:10 -0400

> To: 	graham@mit.edu; jean@mit.edu; hogue@mit.edu; rhwill@mit.edu;
> shutdowns@mit.edu; schedule@mit.edu
> Cc: 	shutdown@plant.mit.edu
> Subject: 	Bldg. 11 Shutdown Request - 7/15
> 
> 
The following shutdown request for Bldg. 11 on 7/15 is for your
information and comment. Would you please let me know if this has your
approval or disapproval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

> Status: Normal
> Building: 11
> Date: 7/15/97
> Day: Tuesday
> Time: 5:30 AM - 7:00 AM
> System: Domestic hot and cold water
> Duration: 1 1/2 hours
> Reason: 
> Connect sink to water system
> 
> Effect: 
> Loss of hot and cold domestic water.
> 
> 