The following requested shutdown for Bldg.7 - 201, 205 and 208 on 7/9
is for your information and comment. Would you please let me know if
this has your approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
Building: 7 - 201, 205 and 208
System: Chilled water (air conditioning)
Date: 7/9
Day: Wednesday
Time: 7:30 AM - 3:00 PM
Duration: 7 1/2 hours
Reason: Relocating fan coil unit within the same room elevating
unit.
Effect: Loss of chilled water (air conditinioning) during
shutdown period.