[38790] in Hotline Meeting
Blg. E51 - 068, 064 Shutdown Request for 7/7
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jul 3 13:56:36 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: mmarshal@MIT.EDU, jstein@MIT.EDU, mchin@MIT.EDU, schedule@MIT.EDU,
shutdowns@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Thu, 3 Jul 1997 13:53:54 -0400
> To: mmarshal@mit.edu; jstein@mit.edu; mchin@mit.edu;
> schedule@mit.edu; shutdowns@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Blg. E51 - 068, 064 Shutdown Request for 7/7
>
>
The following shutdown request for Bldg. E51-068 and 064 on 7/7 is for
your information and comment. Would you please let me know if this has
your approval or disapproval.
Thanks very much.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: E51-068 and 064
> Date: 7/7/97
> Day: Monday
> Time: 7:30 AM - 2:30 PM
> System: Hot and cold domestic water
> Duration: 7 hours
> Reason:
> Relocation of pipes and valves in men's and women's lavoratories (rms.
> 068 and 064).
>
> Effect:
> Loss of use of rooms restrooms 068 and 064 and drinking fountains,
> kitchen faucets in old wing of E51.
>
>