[38779] in Hotline Meeting
RE: Revision 2-Bldgs. 2, 4, 6, 8, 10, 12 & 14 Approved Shutdown -
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jul 2 08:59:58 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>,
"'capozzi@math.mit.edu'" <capozzi@math.mit.edu>,
"'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>,
"'jcentor@mit.edu'" <jcentor@MIT.EDU>,
"'cwilkes@mit.edu'"
<cwilkes@MIT.EDU>,
"'gladyso@mit.edu'" <gladyso@MIT.EDU>,
"'rroscoe@mit.edu'" <rroscoe@MIT.EDU>,
"'sheahan@mit.edu'"
<sheahan@MIT.EDU>,
"'naylor@mit.edu'" <naylor@MIT.EDU>,
"'rrhonda@mit.edu'" <rrhonda@MIT.EDU>,
"'adams@mitlns.mit.edu'"
<adams@mitlns.mit.edu>,
"'elp@mit.edu'" <elp@MIT.EDU>, "'farideh@mit.edu'" <farideh@MIT.EDU>,
"'carolr@mit.edu'"
<carolr@MIT.EDU>,
"'sdl-adm-lib@mit.edu'" <sdl-adm-lib@MIT.EDU>,
"'mleen@mit.edu'" <mleen@MIT.EDU>, "'genh@mit.edu'" <genh@MIT.EDU>,
"'annab@mit.edu'" <annab@MIT.EDU>,
"'jobrien@mit.edu'" <jobrien@MIT.EDU>,
"'otten@mit.edu'" <otten@MIT.EDU>, "'ndk@mit.edu'" <ndk@MIT.EDU>,
"'dhenry5@mit.edu'" <dhenry5@MIT.EDU>, "'ads@mit.edu'" <ads@MIT.EDU>,
"'bkaynor@mit.edu'" <bkaynor@MIT.EDU>,
"'leisan@mit.edu'"
<leisan@MIT.EDU>,
"'smartin@mit.edu'" <smartin@MIT.EDU>,
"'bdavis@mit.edu'" <bdavis@MIT.EDU>,
"'csnyder@mit.edu'"
<csnyder@MIT.EDU>, vonkrogh@MIT.EDU,
decarli@MIT.EDU
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, A-Zone <A-Zone@MIT.EDU>,
B-Zone
<B-Zone@MIT.EDU>, sdverify@MIT.EDU, bmurphy@MIT.EDU,
hoffman@MIT.EDU, larugsi@MIT.EDU
Date: Wed, 2 Jul 1997 10:57:20 -0400
I have been advised that this work cannot be completed in 4 hours but
will be finished in 6 hours. If you have a concern about the extended
time from 3:30 AM to 5:30 AM would you please let me know.
Thank you very much for your patience.
Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 2, 4, 6, 8, 10, 12 & 14
> > Date: 7/2 PM - 7/3 AM
> > Day: Wednesday/Thursday
> > Time: 11:30 PM (7/2) - 5:30AM (7/3) formerly 3:30 AM
> > System: Chill Water
> > Duration: 6 hours
> > Reason:
> > To tie in both ends of new chilled water system and return
> piping in Bldg. 6
> Effect:
> Loss of air conditioning cooling and process load (lasers run
> by chilled water).
>
>
>
>