FW: Approved -Revised -Bldgs. 2, 4, 6, 8, 10, 12 & 14 Requested S

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 1 14:36:01 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Tom Reynolds <treynold@PLANT.MIT.EDU>, dcarlson@MIT.EDU, cappucci@MIT.EDU,
        mmahoney@MIT.EDU, A-Zone <A-Zone@MIT.EDU>, C-Zone
	 <C-Zone@MIT.EDU>,
        sdverify@MIT.EDU
Cc: shutdowns <shutdowns@MIT.EDU>
Date: Tue, 1 Jul 1997 14:33:00 -0400

The following approved revised shutdown for Bldgs. 2, 4, 6, 8, 10, 12
and 14 is for your information.

Note to PPL: Please have standing fans brought to 12-182*, 2-225, 2-032,
4-167, 4-9035, 3-024 and 14-0330. *12-182 is most critical of these
rooms and it is absolutely necessary that a fan be placed there.

Thank you.

> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 2, 4, 6, 8, 10, 12 & 14
> > Date: 7/2 PM - 7/3 AM97
> > Day: Wednesday/Thursday
> > Time: 11:30 PM (7/2) - 3:30AM (7/3)
> > System: Chill Water
> > Duration: 4 hours
> > Reason: 
> > To tie in both ends of new chilled water system and return piping in
> Bldg. 6
> > 
> > Effect: 
> > Loss of air conditioning cooling and process load (lasers run by
> chilled water).
>  
> 
> 