[38765] in Hotline Meeting
Bldg. 12 Shutdown Request - 7/3
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jul 1 11:53:00 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: jcentor@MIT.EDU, bkaynor@MIT.EDU, naylor@MIT.EDU, genh@MIT.EDU,
ads@MIT.EDU, shutdowns@MIT.EDU, schedule@MIT.EDU
Cc: shutdown@plant.mit.edu
Date: Tue, 1 Jul 1997 11:50:23 -0400
> To: jcentor@mit.edu; bkaynor@mit.edu; naylor@mit.edu; genh@mit.edu;
> ads@mit.edu; shutdowns@mit.edu; schedule@mit.edu
> Cc: shutdown@plant.mit.edu
> Subject: Bldg. 12 Shutdown Request - 7/3
>
>
The following shutdown request for Bldg. 12 on 7/3 is for your
information and comment. Would you please let me know if this has your
approval or not.
Thank you.
Andrea Nichols
Operations Center
8-7872
> Status: Normal
> Building: 12
> Date: 7/3/97
> Day: Thursday
> Time: 6:00 AM - 12 Noon
> System: Chilled Water Pump
> Duration: 6 hours
> Reason:
> Replace leaking chilled water pump
>
> Effect:
> Loss of chilled water during shutdown.
>
>