[38744] in Hotline Meeting
RE: Bldg. 26 - Request for Normal Electrical Power Shutdown - 7/1
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 27 13:47:01 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'gfp170@mitrlevm.mit.edu'" <gfp170@mitrlevm.mit.edu>,
"'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'rmbessette@mit.edu'" <rmbessette@MIT.EDU>,
"'dudley@mit.edu'" <dudley@MIT.EDU>,
"'shutdowns@mit.edu'"
<shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Fri, 27 Jun 1997 13:44:29 -0400
> The following requested shutdown for Bldg. 26 on 7/17 PM (11:00 PM)
> thru 7/18 AM (7:00 AM) is for your information and comment. Would you
> please let me know if this has your approval or not.
>
> This is phase 2 of a 2-phase shutdown. Phase 1 of this work was
> completed this morning at 7:00 AM.
>
> Thanks very much.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> Status: Normal
> Building: 26
> Date: 7/17 - 7/18
> Day: Thursday
> Time: 11:00 PM - 7:00 AM
> System: Normal Electrical Power
> Duration: 8 hours
> Reason:
Final phase of New 15KV switch installation. .
> Effect:
> >Loss of Power: access controls, building power, elevators, computers,
> >telephones and lighting; Water: hot domstic water only; Air: supply
> >ventilation, supply cooling, supply heating, laboratory exhaust air,
> general
> exhaust air and toilet exhaust air.
>
>
>