FW: Approved - Bldg. Bldg. 1-139 Shutdown Request for 6/30
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 27 12:55:40 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU, ksutherl@MIT.EDU,
C-Zone <C-Zone@MIT.EDU>, sdverify@MIT.EDU
Cc: Paul McCafferty <pmccaffe@PLANT.MIT.EDU>, shutdowns
<shutdowns@MIT.EDU>
Date: Fri, 27 Jun 1997 12:53:11 -0400
The following approved shutdown for Bldg. 1 - 139 on 6/30 is for your
information.
> Andrea Nichols
> Operations Center
> 8-7872
>
> > Status: Normal
> > Building: 1 - 139
> > Date: 6/30/97
> > Day: Monday
> > Time: 7:00 AM - 3:00 PM
> > System: Chillled Water
> > Duration: 8 hours
> > Reason:
> > Removing two fan coil units
> >
> > Effect:
> > Loss of chilled water in room 139 only.
Note to PPL: Please note comments on hard copy of shutdown re valve type
and location.
> >
> >
>