FW: Approved - Bldg. 1 - 139 Shutdown Request for 6/30

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 27 12:02:02 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU, ksutherl@MIT.EDU,
        C-Zone <C-Zone@MIT.EDU>, sdverify@MIT.EDU
Cc: Paul McCafferty <pmccaffe@PLANT.MIT.EDU>, shutdowns
	 <shutdowns@MIT.EDU>
Date: Fri, 27 Jun 1997 11:58:59 -0400

The following approved shutdown for Bldg. 1 - 139 on 6/30 is for your
information. *Physical Plant: Please note work comments on second page
of hard copy of shutdown.

> Andrea Nichols
> Operations Center
> 8-7872
> 
> > Status: Normal
> > Building: 1 - 139
> > Date: 6/30/97
> > Day: Monday
> > Time: 7:00 AM - 3:00 PM
> > System: Low pressure steam
> > Duration: 8 hours
> > Reason: 
> > Removing radiator
> > 
> > Effect: 
> > None - steam is already off in this room. *PPL - Please note - will
> require 2 men and a 10 to 12 foot ladder.
> > 
> > 
> 