FW: Approved -W16 Asbestos Removal Notification/Bldg. Shutdown Re

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Thu Jun 26 09:03:08 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Jack Narcotta <JNarcott@PLANT.MIT.EDU>, dcarlson@MIT.EDU, cappucci@MIT.EDU,
        mmahoney@MIT.EDU, D-Zone <D-Zone@MIT.EDU>, jhawes@MIT.EDU,
        sdverify@MIT.EDU, tr6@MIT.EDU
Cc: Chris Salter <CSalter@PLANT.MIT.EDU>,
        Neil Tomlinson
	 <NTomlins@PLANT.MIT.EDU>,
        shutdowns <shutdowns@MIT.EDU>
Date: Thu, 26 Jun 1997 09:00:39 -0400

The following approved shutdown/asbestos removal for W16 (Kresge) on 7/1
- 7/10 is for your information.
> Andrea Nichols
> Operations Center
> 8-7872
> 
> Status: Normal
> Building: W16 - 012, 019, 032A
> Date: 7/1/10
> Day: Tuesday (7/1) thru Wednesday (7/10)
> Time: 7:00 AM - 3:00 PM each day  - 7:00 PM + (7/10)
> System: bldg. power, supply ventilation, supply cooling
> Duration: 10 days
> Reason: 
> asbestos removal for all piping in mechanical rooms listed above.
> 
> Effect: 
> >There will be no building electrical power, supply ventilation,
> supply
> >cooling or high pressure steam in any of the mechanical rooms listed
> above during the shutdown period.
> 
> 
> 