RE: Approved -Bldg. NW14 Shutdown Request - 6/24 - 25

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 24 12:41:50 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: dcarlson@MIT.EDU, cappucci@MIT.EDU, mmahoney@MIT.EDU,
        D-Zone
	 <D-Zone@MIT.EDU>, jmannion@MIT.EDU, sdverify@MIT.EDU,
        Andrea Nichols
	 <andrea@PLANT.MIT.EDU>
Cc: shutdowns <shutdowns@MIT.EDU>
Date: Tue, 24 Jun 1997 12:39:25 -0400


> From: 	Andrea Nichols
> Sent: 	Thursday, June 19, 1997 9:27 AM
> To: 	'dcarlson@mit.edu'; 'cappucci@mit.edu'; 'mmahoney@mit.edu';
> D-Zone; 'jmannion@mit.edu'; 'sdverify@mit.edu'
> Cc: 	'shutdowns'
> Subject: 	FW: Revised Approved -Bldg. NW14 Shutdown Request - 6/24
> - 25
> 
> The following approved shutdown for  Bldg. NW14 on 6/24 and 6/25 is
> for your information.
> Andrea Nichols
> Operations Center
> 8-7872
> 
> Status: Normal
> Building: NW14
> Date: 6/24/25 (was initially requested for 7/24-25)
> Day: Tuesday and Wednesday
> Time: 7:00 AM - 3:00 PM each day
> System: CV3 perimeter heating hot water system
> Duration: 2 days
> Reason: 
> >Installation of perimeter heating hot water control valves to serve
> NW14-2110, 2108 and 2104.
> 
> Effect: 
> Loss of perimeter heating hot water for entire building.
> 
> 
> 
> 