[38709] in Hotline Meeting

home help back first fref pref prev next nref lref last post

FW: Approved -Bldg. 10 Shutdown Request for 6/25

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 24 08:59:02 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: Tom Reynolds <treynold@PLANT.MIT.EDU>, dcarlson@MIT.EDU, cappucci@MIT.EDU,
        mmahoney@MIT.EDU, anton@MIT.EDU, C-Zone
	 <C-Zone@MIT.EDU>,
        sdverify@MIT.EDU
Cc: shutdowns <shutdowns@MIT.EDU>
Date: Tue, 24 Jun 1997 08:56:38 -0400

The following approved shutdown for Bldg. 10 on 6/25 is for your
information.
> Andrea Nichols
> Operations Center
> 8-7872
> 
> Status: Normal
> Building: 10 - 4th floor
> Date: 6/25/97
> Day: Wednesday
> Time: 7:00 AM - 11:00 AM
> System: Air Handler #3 (supply vent. & cooling)
> Duration: 3 hours
> Reason: 
> Demolition/removal of ducts in offices 10-400 thru 404,
> 
> Effect: 
> >Loss of supply ventilation and supply cooling on entire 4th floor.
> Fan coil units will be operational however.
> 
> 
> 