Bldg. 11 Shutdown Request - 6/20

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Tue Jun 17 09:07:10 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'graham@mit.edu'" <graham@MIT.EDU>,
        "'sdiamond@mit.edu'"
	 <sdiamond@MIT.EDU>,
        "'hogue@mit.edu'" <hogue@MIT.EDU>, "'rhwill@mit.edu'" <rhwill@MIT.EDU>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, C-Zone <C-Zone@MIT.EDU>
Date: Tue, 17 Jun 1997 09:08:23 -0400

>To: 	graham@mit.edu; sdiamond@mit.edu; hogue@mit.edu; rhwill@mit.edu;
shutdowns@mit.edu
Cc: 	shutdown@plant.mit.edu; C-Zone
Subject: 	Bldg. 11 Shutdown Request - 6/20


The following shutdown request for Bldg. 11 on 6/20 is for your
information and comment. Would you please let me know if this has your
approval or disapproval.

Thank you.

Andrea Nichols
Operations Center
8-7872

Status: Normal
Building: 11
Date: 6/20/97
Day: Friday
Time: 3:00 AM - 7:00 AM
System: Cold Domestic Water
Duration: 4 hours
Reason: 
>Renovation  1st floor. Work will take place in the ceiling space of the
basement.

Effect: 
>Loss of domestic cold water - no restroom facilities, kitchen faucets or
drinking fountains will be available.