FW: Approved -Bldg. 26 - Request for Normal Electrical Power Shutdown - 6/26 PM - 6/27 AM

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 13 16:35:13 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: William Wohlfarth <wpwohlfa@PLANT.MIT.EDU>,
        "'dcarlson@mit.edu'"
	 <dcarlson@MIT.EDU>,
        "'cappucci@mit.edu'" <cappucci@MIT.EDU>,
        "'mmahoney@mit.edu'" <mmahoney@MIT.EDU>, B-Zone <B-Zone@MIT.EDU>,
        "'sdverify@mit.edu'" <sdverify@MIT.EDU>
Cc: Neil Tomlinson <NTomlins@PLANT.MIT.EDU>,
        "'cust-coach@mit.edu'"
	 <cust-coach@MIT.EDU>,
        'shutdowns' <shutdowns@MIT.EDU>
Date: Fri, 13 Jun 1997 16:36:41 -0400

The following approved shutdown for Bldg. 26 on 6/27 PM - 6/27 AM is for
your information.

>This is phase I of a 2-phase shutdown. The second and final phase for
>this work will take place in about 3 weeks. The requested hours and time
>frame would be the same. When I receive more information about this, I
>will forward a second shutdown request to you.
>
>Thanks very much.
>
>Andrea Nichols
>Operations Center
>8-7872
>
>Status: Normal
>Building: 26
>Date: 6/26/27
>Day: Thursday
>Time: 11:00 PM - 7:00 AM
>System: Normal Electrical Power
>Duration: 8 hours
>Reason: 
>New 15KV switch installation. Will be done in 2 phases. 
>
>Effect: 
>>Loss of Power: access controls, building power, elevators, computers,
>>telephones and lighting; Water: hot domstic water only; Air: supply
>>ventilation, supply cooling, supply heating, laboratory exhaust air, general
>exhaust air and toilet exhaust air.
>
>
>