[38620] in Hotline Meeting
RE: Bldg. 12 Rescheduled Requested Shutdown- Now for 6/18
daemon@ATHENA.MIT.EDU (Andrea Nichols)
Wed Jun 11 15:54:02 1997
From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'schedule@mit.edu'" <schedule@MIT.EDU>,
"'naylor@mit.edu'"
<naylor@MIT.EDU>, "'genh@mit.edu'" <genh@MIT.EDU>,
"'jcentor@mit.edu'" <jcentor@MIT.EDU>,
"'jbartels@mit.edu'" <jbartels@MIT.EDU>, "'ads@mit.edu'" <ads@MIT.EDU>
To: "'sjbird@mit.edu'" <sjbird@MIT.EDU>,
"'schedule@mit.edu'"
<schedule@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
"'bkaynor@mit.edu'" <bkaynor@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>
Date: Wed, 11 Jun 1997 15:53:47 -0400
The following rescheduled shutdown request for cold water for
Bldg. 12 now on 6/18 is for your information and comment. This
shutdown will affect domestic cold water only for the building.
>Would you please let me know if this has your
>approval or disapproval.
>
>Thanks very much.
>
>Andrea Nichols
>Operations Center
>8-7872
>
>Status: Normal
>Building: 12 - 065 (also entire bldg.)
>Date: 6/18/97
>Day: Wednesday
>Time: 7:00 AM - 9:00 AM
>System: Domestic Cold
>Duration: 2 hours
>Reason:
>Deluge shower and eye wash installation.
>
>Effect:
>>Even though work is primarily being done in 12-065 this shutdown would mean
>>the loss of cold domestic water for entire building. This would affect
>>restroom facilities, kitchen faucets and drinking fountains.
>
>
>