Bldg. 2 - 2nd & 3rd Floor Shutdown Request - 6/11

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Mon Jun 9 09:01:32 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'"
	 <schedule@MIT.EDU>,
        "'capozzi@math.mit.edu'"
	 <capozzi@math.mit.edu>,
        "'nolan@math.mit.edu'"
	 <nolan@math.mit.edu>,
        "'juliec@mit.edu'" <juliec@MIT.EDU>, "'mbj@mit.edu'" <mbj@MIT.EDU>
Cc: Clint McFarland <cmcfarla@PLANT.MIT.EDU>,
        "'shutdown@plant.mit.edu'"
	 <shutdown@plant.mit.edu>
Date: Mon, 9 Jun 1997 09:02:30 -0400

>To: 	shutdowns@mit.edu; schedule@mit.edu; capozzi@math.mit.edu;
nolan@math.mit.edu; juliec@mit.edu; mbj@mit.edu
Cc: 	Clint McFarland; shutdown@plant.mit.edu
Subject: 	Bldg. 2 - 2nd & 3rd Floor Shutdown Request - 6/11


The following shutdown request for Bldg. 2 - 2nd floor on 6/11 is for
your information and comment. Would you please let me know if this has
your approval or disapproval.

Thanks very much.

Andrea Nichols
Operations Center
8-7872

Status: Normal
Building: 2 - 2nd  & 3rd floors only
Date: 6/11/97
Day: Wednesday
Time: 8:00 AM - 4:00 PM
System: Chilled Water
Duration: 8 hours
Reason: 
have to replace 4 ball valves

Effect: 
Loss of air conditioning during shutdown period.