[38595] in Hotline Meeting

home help back first fref pref prev next nref lref last post

Bldg. 26 - 4th Floor only 6/10 Shutdown Request

daemon@ATHENA.MIT.EDU (Andrea Nichols)
Fri Jun 6 09:23:02 1997

From: Andrea Nichols <andrea@PLANT.MIT.EDU>
To: "'adams@mitlns.mit.edu'" <adams@mitlns.mit.edu>,
        "'gfp170@mitrlevm.mit.edu'" <gfp170@mitrlevm.mit.edu>,
        "'shutdowns@mit.edu'" <shutdowns@MIT.EDU>,
        "'schedule@mit.edu'" <schedule@MIT.EDU>
Cc: Shutdown <Shutdown@PLANT.MIT.EDU>, B-Zone <B-Zone@MIT.EDU>
Date: Fri, 6 Jun 1997 09:24:29 -0400

>To: 	adams@mitlns.mit.edu; gfp170@mitrlevm.mit.edu; shutdowns@mit.edu;
schedule@mit.edu
Cc: 	shutdown@plant.mit.edu; B-Zone
Subject: 	Bldg. 26 - 4th Floor only 6/10 Shutdown Request


The following shutdown request for Bldg. 26 - 4th floor on 6/10 is for
your review and comment. Would you please let me know if this has your
approval or disapproval.

Thank you.

Andrea Nichols
Operations Center
8-7872

Status: Normal
Building: 26-4th floor
Date: 6/10/97
Day: Tuesday
Time: 8:00 AM - 4:00 PM
System: Chilled  and heating hot water
Duration: 9 hours
Reason: 
New fan coil units tie -in. Replacement of radiator's control valve.

Effect: 
>Loss of chilled water and heating hot water. Chilled water serves air
conditioning and process loads (laser).



home help back first fref pref prev next nref lref last post