[38072] in Hotline Meeting
Re: Shutdown Request - Bldg. E40 - 5/1
daemon@ATHENA.MIT.EDU (Jonathon Weiss)
Tue Apr 29 18:17:55 1997
From: Jonathon Weiss <jweiss@MIT.EDU>
To: Andrea Nichols <andrea@PLANT.MIT.EDU>
Cc: "'mmarshal@mit.edu'" <mmarshal@MIT.EDU>,
"'shutdowns@mit.edu'" <shutdowns@MIT.EDU>, E-Zone <E-Zone@MIT.EDU>
Cc: ops@MIT.EDU, network@MIT.EDU, dcns-cluster@MIT.EDU
In-Reply-To: Your message of "Tue, 29 Apr 1997 14:08:52 EDT."
<c=US%a=_%p=MIT%l=PLANTNT-970429180852Z-5270@PLANT.MIT.EDU>
Date: Tue, 29 Apr 1997 18:16:30 EDT
Will e40-008 be included in this shutdown? I suspect that it is not
in what is considered the southwest part of the building, but I need
to confirm that.
Jonathon Weiss
jweiss@mit.edu
Athena Server Operations
> The following shutdown request is for your information and comment.
> Would you please let me know if this has your approval or not.
>
> Thank you.
>
> Andrea Nichols
> Operations Center
> 8-7872
>
> Building: E-40 - Southwest half - all floors
> System: Chill water - Fan Coil Units
> Date: 5/1
> Day: Thursday
> Time: 7:30 AM - 11:30 AM
> Duration: 4 hours
> Reason: Tie in new Fan Coil Unit
> Effect: Loss of supply cooling (air conditiong)