Building:	E-40 - Southwest half - all floors
System:	Chill water - Fan Coil Units
Date:		5/1
Day:		Thursday
Time:		7:30 AM - 11:30 AM
Duration:	4 hours
Reason:	Tie in new Fan Coil Unit
Effect:		Loss of supply cooling (air conditiong)