Brian,
As scheduled, the drops in B12 182 were installed and tested.
Sixty drops were installed in total. All but 12-182 201 have line
cords.
Jerry made me aware of a missing location under the electrical
panel. I noticed this on the general contractors print last week and
questioned him about it. At that time he discounted it.
Don, the project superintendent informs me that "everyone"
is now aware it and he has been given direction to take no action.
After speaking with Jerry, we both agree that it would be difficult
to install this location at a later date. As Don stated, he would
be required to open the wall and core a hole through the floor.
Conduit would then be required, followed by the jack installation
This would be time consuming at least.
At this time, everything is ready for you.