The following filter change notification/shutdown request for Bldg. 18
for 3/13 is for your information and comment. Would you please let me
know if this has your approval or not.
Thank you.
Andrea Nichols
Operations Center/PM Office
8-7872
Building: 18
System: Supply Fans 1,(Center Bldg. Labs) 6 (Hood Make-up Fan) and 7
(hood makeup fan)
Date: 3/13
Day: Thursday
Time: 7:00 AM - 1:00 PM
Duration: 4 1/2 hours within above time frame
Reason: 129 Filter Changes
Effect: Supply Fan 1 will be down for 2.5 hours. With this
Supply Fan, there will be a loss of supply ventilation, cooling
and heating.
Supply Fans 6 and 7 will be down one at a time for one hour at
a time. Loss of hood make-up air should be minimal.