Emergency Shutdown - Bldg. E23 and E25 - 3/10 and 3/11
daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Mar 5 15:03:17 1997
Date: Wed, 5 Mar 1997 14:57 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, cust-coach@MIT.EDU, roge@med.mit.edu,
edwa@med.mit.edu, schedule@MIT.EDU, sdl-adm-lib@MIT.EDU,
jmganno@MIT.EDU, shyoung@MIT.EDU
X-Envelope-To: cust-coach@mit.edu, jmganno@mit.edu, opsnote@mit.edu,
schedule@mit.edu, sdl-adm-lib@mit.edu, shutdowns@mit.edu, shyoung@mit.edu
X-Vms-To:
IN%"shutdowns@mit.edu, opsnote@mit.edu, cust-coach@mit.edu, roge@med.mit.edu, e
dwa@med.mit.edu, schedule@mit.edu, sdl-adm-lib@mit.edu, jmganno@mit.edu, shyo
ung@mit.edu"
The following emergency shutdown for Bldgs. E23 and E25 for 3/10 and
3/11 is for your information and comment. Would you please let me know
if this has your approval or not.
Thanks.
Andrea Nichols
Operations Center
8-7872
Emergency
Building: E23 and E25
System: Chilled Water
Date: 3/10 and 3/11
Day: Mondan and Tuesday
Time: 7:00 AM 3/10 - 7:00 AM - 3/11
Duration: 24 hours
Reason: To tie in to East Plant pipint supply and return
Effect: Loss of air conditioning for fan coil units/computer
room cooling. Air Handlers will remain operational however.