Critical Requested Shutdown - Bldg. 8 - 331, 329A and 241 - 3/7

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Mar 5 14:00:32 1997

Date: Wed, 5 Mar 1997 13:56 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, acherron@MIT.EDU, croberts@MIT.EDU
X-Envelope-To: acherron@mit.edu, croberts@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, acherron@mit.edu, croberts@mit.edu"

The following critical shutdown request for Bldg. 8 - 331, 329A and 241
for 3/7 is for your information and comment. Would you please let me
know if this has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Critical
Building:       8 - 331, 329A and 241
System:         Hood Exhaust Fan - PM#702574
Date:           3/7/97
Day:            Friday
Time:           9:00 AM - 12 Noon
Duration:       3 hours
Reason:         To balance fan and complete work required to eliminate
                vibration.
Effect:         Loss of exhaust laboratory air during shutdown period.