Requested Critical Shutdown Bldgs. 56 and 16 - 3/6/97

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Wed Mar 5 11:07:16 1997

Date: Wed, 5 Mar 1997 11:03 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mmahoney@MIT.EDU, schedule@MIT.EDU, lindlore@MIT.EDU,
        mbj@MIT.EDU, blair@mitvma.mit.edu, scotts@mitvma.mit.edu,
        shyoung@MIT.EDU, jmganno@MIT.EDU
X-Envelope-To: jmganno@mit.edu, lindlore@mit.edu, mbj@mit.edu,
 mmahoney@mit.edu, schedule@mit.edu, shutdowns@mit.edu, shyoung@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, mmahoney@mit.edu, schedule@mit.edu, lindlore@mit.edu, mb
   j@mit.edu, blair@mitvma.mit.edu, scotts@mitvma.mit.edu, shyoung@mit.edu, jmga
   nno@mit.edu"

The following requested Critical shutdown for Bldgs. 56 and 16 for 3/6
is for your information and comment. Would you please let me know if
this has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Critical
Building:       56 and 16
System:         Domestic water booster pump (Bldg. 56)
Date:           3/6/97
Day:            Thursday
Time:           6:00 PM - 8:00 PM
Duration:       2 hours
Reason:         Maintenance
Effect:         Bldg. 56 and 16 may experience low domestic water
                pressure.