Ooop! - Wrong month! - Shutdown Request - Bldg. E19 6th & 7th Flrs. -

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Tue Feb 25 09:23:25 1997

Date: Tue, 25 Feb 1997 09:18 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, opsnote@MIT.EDU, cust-coach@MIT.EDU, wbarrett@MIT.EDU,
        dlfair@MIT.EDU, edie@mitvmc.mit.edu, cashaw@MIT.EDU,
        lambert@mitvma.mit.edu, honiker@MIT.EDU
X-Envelope-To: cashaw@mit.edu, cust-coach@mit.edu, dlfair@mit.edu,
 honiker@mit.edu, opsnote@mit.edu, shutdowns@mit.edu, wbarrett@mit.edu
X-Vms-To: 
 IN%"shutdowns@mit.edu, opsnote@mit.edu, cust-coach@mit.edu, wbarrett@mit.edu, d
   lfair@mit.edu, edie@mitvmc.mit.edu, cashaw@mit.edu, lambert@mitvma.mit.edu, h
   oniker@mit.edu"

Correction! The following shutdown request is for March, not April. No
wonder the dates and days didn't match. Here is the correct
information.

Thank you for your patience.

                        Andrea

The following shutdown request for Bldg. E19 - 6th and 7th floors for
3/12, 13 and 14 is for your information and comment. Would you please
let me know if this has your approval or not.

Thank you.

Andrea Nichols
Operations Center
8-7872

Building:       E19 - 6th and 7th floors
System:         Air Handler 7-1, Supply Air/Return Air systems
Date:           3/12, 13 and 14
Day:            Wednesday Thursday and Friday
Time:           6:00 AM (3/12) - 3:00 PM (3/14)
Duration:       72 hours
Reason:         Fan System replacement within E19-701 Mechanical Rm.
Effect:         Loss of chilled water, supply ventilation, supply
                cooling, supply heating and fire alarm system.