Bldg. 18 Filter Change Notification/Shutdown Request - 2/26

daemon@ATHENA.MIT.EDU (OPCTEMP2%MITPPL.bitnet@mitvma.mit.)
Fri Feb 21 09:26:59 1997

Date: Fri, 21 Feb 1997 09:23 EDT
From: OPCTEMP2%MITPPL.bitnet@mitvma.mit.edu
To: shutdowns@MIT.EDU, mbj@MIT.EDU
X-Envelope-To: mbj@mit.edu, shutdowns@mit.edu
X-Vms-To: IN%"shutdowns@mit.edu, mbj@mit.edu"

The following filter change notification/shutdown request for Bldg. 18
for 2/26 is for your information and comment. Would you please let me
know if this has your approval or not.

Thanks very much.

Andrea Nichols
Operations Center/PM Office
8-7872

Building:       18 - Entire Building
System:         Supply Fan 1 - Supply ventilation, cooling and heating
Date:           2/26/97
Day:            Wednesday
Time:           7:00 AM - 12 noon
Duration:       3 hours within above time frame
Reason:         169 filter changes
Effect:         Loss of supply ventilation, cooling and heating during
                shutdown period.